The issues of connecting wind power plants (WPP) to the power-supply system and their joint operation are currently gaining relevance due to the growth of their capacities and an abruptly variable pattern of its delivery to the grid. The paper presents the analysis of standards, recommendations and regulations related to connection and operation of WPPs as part of the power-supply system. The developed mathematical model of the Ushakovskaya WPP is used to analyze its main operating modes. Practical recommendations for changing the scheme of power generation of the plant at increased capacity are given with due regard to the standard requirements.