Chapter 1Free to read

The design and procurement process


Published Copyright © Institute of Physics and Engineering in Medicine 2017
Pages 1-1 to 1-16

Download ePub chapter

You need an eReader or compatible software to experience the benefits of the ePub3 file format.

Download complete PDF book, the ePub book or the Kindle book

Export citation and abstract

BibTeX RIS

Share this chapter

978-0-7503-1440-4

Abstract

Chapter 1 covers the overall design and procurement process for the various radiotherapy facilities before specific chapters on the different types of equipment and techniques. This includes the business planning process, facility construction, equipment procurement, acceptance and commissioning—emphasising all the professions who need to be in the design and implementation team to ensure a successful outcome.

This article is available under the terms of the IOP-Standard Books License

IPEM Report 75 2nd Edition is an update of IPEM Report Number 75, a report produced by the Institute of Physics and Engineering in Medicine

Whilst every attempt is made to provide useful and accurate information, neither IPEM, nor the members of IPEM nor any other persons contributing to the content of this publication make any warranty, express or implied, with regard to the accuracy or completeness of the information contained in it. Nor do any such parties assume any liability with respect to the use, or consequences of use, of the information contained in this publication.

All rights reserved. No part of this publication may be reproduced, stored in a retrieval system or transmitted in any form or by any means, electronic, mechanical, photocopying, recording or otherwise, without the prior permission of the publisher, or as expressly permitted by law or under terms agreed with the appropriate rights organization. Multiple copying is permitted in accordance with the terms of licences issued by the Copyright Licensing Agency, the Copyright Clearance Centre and other reproduction rights organisations.

Permission to make use of IOP Publishing content other than as set out above may be sought at permissions@iop.org.

Patrick Horton and David Eaton have asserted their right to be identified as the authors of this work in accordance with sections 77 and 78 of the Copyright, Designs and Patents Act 1988.

1.1. Introduction

The need for new equipment, the upgrading of an existing facility or the development of a new radiotherapy facility can arise from a number of circumstances. These include:

  • •  
    the need to replace unreliable equipment,
  • •  
    the need to have new equipment with features enabling current accepted clinical practice,
  • •  
    the need for additional equipment to increase treatment capacity to meet increasing demand or treatment complexity and keep waiting times for treatment to specified standards,
  • •  
    the need for a new cancer centre to replace an outdated facility for a variety of reasons,
  • •  
    provision of a satellite treatment unit to an existing centre to increase treatment capacity and provide more local patient treatments or
  • •  
    the need to meet the NHS England Radiotherapy Service Specifications (NHS Commissioning Board 2013).

In many instances, the first and second needs will both apply. Expenditure on new facilities or new equipment is termed a capital project within the NHS. Similar arrangements will apply in private hospitals and charitable institutions.

The stages in progressing a capital project are set out in table 1.1. The stages outlined in the table may not be followed exactly, but some elements of each stage will be required. The NHS Trust or organisation should appoint a senior member of staff as the project officer and he/she will be responsible for the overall management of the project. This will include preparation of the business case for the funding and the project brief and, in the case of major schemes, the appointment of an external project manager (often the architect or the organisation employing him/her) or a private consortium for a public private partnership (PPP). A realistic timetable must be agreed for design, equipment selection, letting contracts, construction, equipment installation, and acceptance and equipment commissioning for clinical use, with a contingency built in to allow for unavoidable slippage in the project, e.g. poor crane utilisation due to high winds. Gantt charts are invaluable to show the timetabling and interaction of the individual activities within the project and to help ensure that each takes place on a logical and timely basis. A more detailed discussion of the stages follows below.

Table 1.1.  Stages in the introduction of new equipment.

Strategic proposal
Business case
 Strategic Outline Programme (SOP)
 Strategic Outline Case (SOC)
 Outline Business Case (OBC)
 Full Business Case (FBC)
Design and design team
Tenders and contracts
 Buildings and services
 Equipment
Construction
Acceptance and handover
 Buildings and services
 Equipment
Commissioning
 Clinical services
 Equipment
Evaluation

The roles and responsibilities of the medical physicists available to the development will vary according to local circumstances and the expertise of the individuals available. At minimum there must be a medical physics expert (MPE) in radiotherapy and a radiation protection adviser (RPA). Medical physics involvement in all of the following activities (in the order in table 1.1) is essential for a successful project:

  • •  
    Participation in the design of the radiation facility.
  • •  
    Specification of the necessary radiation protection.
  • •  
    Writing the specification for the equipment required.
  • •  
    Scientific and technical advice during the selection of the equipment.
  • •  
    Monitoring of the construction of the facility to ensure that the radiation protection requirements and the service requirements for the selected equipment are met.
  • •  
    Liaison with the equipment supplier and co-ordination of the equipment installation.
  • •  
    Acceptance testing of the equipment with the supplier's installation engineers.
  • •  
    Responsibility for the radiation survey of the new facility and electrical safety of the installed equipment.
  • •  
    Commissioning of the equipment prior to clinical use.
  • •  
    Establishment of quality assurance regimes, documentation and training.

Medical physicists may also undertake additional roles, e.g. some of the project management.

1.2. Strategic proposal and business case for a new development

Due to the capital cost and possibly revenue costs, the project will require a business case for its approval in the public sector; similar needs will apply in the private and charitable sectors. In many organisations a strategic proposal can be submitted at the start of the annual capital planning cycle, sometimes using a standard pro-forma to help ensure that all the relevant information to enable a decision is available. The proposal may include the following topics for a successful development, depending on its magnitude:

  • •  
    The purpose of the application.
  • •  
    The strategic context.
  • •  
    The case for change, including the difficulties or deficiencies that currently exist, their cause(s) and the proposed solution. It is important to include substantiated evidence to show the existence and the extent of the problem.
  • •  
    Benefits, both service and financial.
  • •  
    Risks.
  • •  
    Available options (including 'do nothing') and their consequences.
  • •  
    Preferred option.
  • •  
    Procurement route.
  • •  
    Anticipated costs—capital and revenue.
  • •  
    Management arrangements, both organisational and financial.

Business cases are a mandatory part of the planning, approval, procurement and delivery of investments in the public sector. A good business case provides an organisation with the evidence to support its decision making and provides assurance to other stakeholders, e.g. service commissioners, that it has acted responsibly. The 'Five Case Model' of the Office of Government Commerce (2013) is the recommended standard for the preparation of business cases and is used extensively in the public sector. The Five Case Model comprises the following five key components:

  • •  
    The strategic case. This sets out the strategic context and the case for change, together with the investment objectives for the scheme.
  • •  
    The economic case. This demonstrates that the organisation has selected the choice for development which best meets the existing and future needs of the service and optimises value for money.
  • •  
    The commercial case. This outlines the content of the proposed deal.
  • •  
    The financial case. This confirms the funding arrangements and explains any effects on the balance sheet of the organisation, i.e. affordability.
  • •  
    The management case. This demonstrates that the scheme is achievable and details the plans for the successful delivery of the scheme to cost, time and quality standards.

The business planning process using the Five Case Model is an iterative process using the five headings above with increasing detail as the proposal progresses through four phases, each requiring approval before proceeding to the next. These phases are:

  • •  
    Strategic Outline Programme (SOP).
  • •  
    Strategic Outline Case (SOC).
  • •  
    Outline Business Case (OBC).
  • •  
    Full Business Case (FBC).

Guidance on the process and detailed templates for the four phases above are available from the Office of Government Commerce (2013). More information on the approval process in England is available from NHS England (2013; NHS Business Case Approval Process—Capital Investment, Property, Equipment and ICT) which also has pro-formas and checklists. For radiation users this guidance is also available in the RCR (2012) publication Writing a Good Business Case, intended for non-financial persons and having a good explanation of the terminology. In 2014, the NHS Trust Development Authority modified the Five Case Model (Capital Regime and Investment Business Case Approvals—Guidance for NHS Trusts) and inserted the clinical quality case between the strategic and economic cases above. This sets out the clinical and patient benefits of the proposal more clearly than might previously have been the situation as part of the strategic case.

Depending on the financial rules of the organisation, a proposal may be classified as a minor capital scheme if the costs are not high and there are no wide implications, e.g. replacement of a kilovoltage treatment unit, or a major capital scheme if the costs are high and there are wider implications such as building or additional staffing costs. The funding of a new project can come from a number of sources. Within the NHS these include:

  • •  
    An internally generated cash surplus by the NHS Trust at year end from unspent capital, depreciation, disposal of assets, revenue surplus, etc.
  • •  
    Capital Investment Loans from the Department of Health on which the NHS Trust pays a fixed rate of interest for the period of the loan and repays the capital at regular intervals.
  • •  
    Central programme capital for central initiatives.

The capital plans of NHS Trusts must be agreed with the NHS Trust Development Authority who review them to ensure they are affordable, achievable and fit with local and strategic priorities. All plans are then agreed with the Department of Health to ensure they are affordable within the overall NHS capital programme.

A major development such as a new cancer centre may necessitate a PPP because of the large capital cost. The most common form of PPP has been the private finance initiative (PFI), where the capital investment is provided by the private sector on the strength of a contract with the NHS Trust over a long period to provide agreed services and the cost of providing the service is borne wholly or in part by the NHS. The private sector recovers its costs over the contract period (often 25 years or more) and assumes a financial, technical and operational risk in the project. Commonly the private sector is a consortium of a construction company, a maintenance company and a bank lender to develop, build, maintain and operate the asset for the period of the contract. At the end of the contract period, the asset either remains with the private sector contractor or is returned to the NHS, depending on the terms of the contract. The purpose of the PFI is to increase private sector involvement in the provision of public services with the perceived benefits of bringing in private sector expertise and lower costs to the taxpayer.

Some organisations may choose to lease the equipment or use a managed equipment service company to reduce the capital outlay.

1.3. Design team

1.3.1. General

The wide range of professionals who may be involved in the planning, construction and commissioning of a radiotherapy treatment facility is shown in table 1.2. The actual number involved will depend on the magnitude of the project and the contractual arrangements.

Table 1.2.  Persons involved in the design and construction of radiotherapy treatment facilities.

Hospital/Trust representatives
 Finance officer
 Oncology business manager
 Planning officer
 Estates/works officer
 RPA
 IT specialist(s)
 Patient and public voice partner
Users
 Radiation oncologists
 Radiotherapy physicists
 Therapy radiographers, including Radiation Protection Supervisor
 Medical physics technical officers
External design team
 Architect
 Structural engineer
 Electrical engineer
 Mechanical engineer
 Quantity surveyor
 Design consultant
Contractors
 Construction company
 Electrical work sub-contractor
 Mechanical work sub-contractor
 Specialised shielding and component (e.g. doors) sub-contractors
Treatment equipment manufacturer
 Installation co-ordinator
 Delivery and rigging sub-contractor
 Installation engineers

1.3.2. Minor capital schemes

For a minor capital scheme, the main activities are most likely to be the selection of the equipment and the adaptation of an existing room to take the new equipment. A small design team is sufficient and can be usually drawn from hospital staff. The team should include:

  • •  
    a representative of the Planning Department (who may also be the project leader),
  • •  
    a radiotherapy physicist,
  • •  
    a radiographer,
  • •  
    a medical physics technical officer and
  • •  
    a member of the Works Department.

The selection of the equipment may be undertaken by a wider group of radiotherapy physicists, radiographers and technical officers, including the radiotherapy physicist and radiographer on the project team.

When the new equipment has been chosen and the installation and adaptation requirements are clear, the project team should also include:

  • •  
    selected representatives of the hospital's approved contractors, e.g. for building and electrical work,
  • •  
    the supplier's representative and
  • •  
    the RPA.

1.3.3. Major capital schemes

For a major capital scheme, e.g. involving the installation of linear accelerator(s) in a new or modified building, there will be more complex issues around the design, construction or alteration of the building and its integration into existing facilities and services. This will require additional expertise from outside the hospital and will usually include an architect, a structural engineer, an electrical engineer and a quantity surveyor. These may all come from the same organisation, depending on the contract arrangements. The project may well be managed at two levels: a smaller project team and a larger design and execution team. The effects of the works and the introduction of new equipment on the maintenance of clinical services will also have to be assessed and any adverse effects minimised. The project team might comprise the following:

  • •  
    a senior member of the Finance Department (who may be the project officer),
  • •  
    a radiation oncologist,
  • •  
    a senior radiotherapy physicist (MPE),
  • •  
    the radiotherapy patient services manager,
  • •  
    a representative of the Planning Department,
  • •  
    a member of the Estates Department and
  • •  
    the selected architect.

The larger design team will report to the project team at regular intervals through one of its members who serves on both teams. The design team will include:

  • •  
    the selected architect (who may be the project manager) and his/her supporting staff,
  • •  
    the representative of the Planning Department,
  • •  
    the senior medical physicist,
  • •  
    relevant radiotherapy physicists,
  • •  
    radiotherapy patient services manager,
  • •  
    relevant senior radiographers,
  • •  
    a medical physics technical officer,
  • •  
    a member of the Estates Department,
  • •  
    the RPA,
  • •  
    IT specialist(s) and
  • •  
    patient and public voice (PPV) partners.

When the building design and the selection of the equipment has been finalised and construction is underway, progress meetings of the design team should also include:

  • •  
    representatives of the construction company,
  • •  
    the structural engineer,
  • •  
    the electrical engineer,
  • •  
    the mechanical engineer and
  • •  
    the equipment supplier's representative.

All project and planning team meetings should be minuted and any changes in the design (variation orders) carefully costed and agreed, as these are often the source of additional expenditure and budget overruns.

The role of the IT specialist(s) is important with modern complex radiotherapy management systems and the sharing of images and large amounts of data between treatment planning and treatment systems. He/she may come from medical physics or the hospital's IT Department, or preferably one from both. The requirements of the equipment vendor's management software should be clearly understood so that it is not compromised by the hospital's general IT requirements. Common practice is to confine the heavy radiotherapy data flows to a separate network (linking the treatment units, planning systems and CT simulators) with a firewall to the hospital network for the import/export of patient administrative information and the import of images from hospital imaging facilities.

1.3.4. Public private partnership

As stated earlier, a major development may entail a PPP to design, construct and operate the facility through a PFI. This requires comprehensive and substantial teams such as those outlined above for a major capital scheme in both the hospital and the construction components of the partnership. The role of the hospital team is to specify the objectives of the new facility, particularly with regard to the range of services to be provided, their volume and expected growth, and check that the completed scheme meets these objectives. The role of the construction company together with its appointed architect will be to design and construct the facility to meet the hospital's objectives for the cost agreed. Whilst construction companies are familiar with mechanical, electrical and structural matters, they are much less familiar with the requirements of radiotherapy and radiation protection legislation and should have a radiotherapy expert and an RPA available to their design and construction teams. It is beneficial to the project if the contractual arrangements allow a dialogue between the hospital's radiotherapy team and RPA and the contactor's expert and RPA so that details of the design, e.g. the planned radiation workload for individual linear accelerators, and radiation protection policy are available to the design team from the earliest possible stage. It is essential that the final design of any radiation facilities, together with the radiation protection calculations to meet the hospital's radiation protection policy, are approved by the hospital's RPA before construction starts. At the conclusion of the project, there must be agreement with the hospital's RPA on the performance of the radiation survey of the new facility and the wide availability of survey results to ensure that the design criteria have been met and the facility is safe for clinical use. The hospital's RPA may also need to notify the Health and Safety Executive if it is a new radiation facility. The maintenance company in the PPP will be familiar with building maintenance but usually less familiar with the technical support usually provided in radiotherapy by medical physics technical officers to ensure high levels of equipment availability for treatment. This issue needs to be discussed long before clinical services commence and a sub-contract with the hospital team may be necessary due to the very specialised nature of the work.

1.4. Process, tenders and contracts

1.4.1. Minor capital schemes

For a minor capital scheme, the starting point will be a specification for the new equipment. This will be drawn up by radiotherapy physicists and radiographers, in conjunction with the radiation oncologists, to meet the clinical need. Prior to finalising the specification it is advisable to have preliminary discussions with manufacturers to ensure that the proposed specification reflects current possibilities. The specification may be in the form of an output based specification which describes what the equipment has to achieve or a detailed specification of the equipment and its performance, or a combination of the two. Specifications must not be written so that only one manufacturer can comply. After approval by the hospital, the specification can be sent to potential suppliers and must be advertised with a clear closing date for offers in the Official Journal of the European Union (OJEU) if it is expected to cost more than a prescribed limit. Current thresholds valid from 1 January 2016 to 3 December 2017 are £106 047 for NHS Trusts and £164 170 for NHS Foundation Trusts. Although these thresholds are based on thresholds in euros, they remain unchanged during this period independent of currency fluctuations. Alternatively, the hospital can use the radiotherapy equipment framework agreement negotiated by the NHS Supply Chain. Using the framework it is possible to set up a mini-competition between suppliers without advertising in the OJEU. Additions to the baseline specification can be agreed between the suppliers and the purchaser. In some circumstances it is possible that a new model of equipment may not be available in the framework.

To evaluate the offers in a uniform and objective manner, the users should develop an option appraisal pro-forma in which each of the identified performance parameters is given a weight according to its relative importance. Each performance parameter can then be scored over a set range for each supplier's equipment on the basis of how closely it matches the desired performance and a weighted total score calculated to indicate which supplier's equipment most closely approaches the ideal solution. It will also be necessary to look at other issues, such as operator and physicist training, maintenance arrangements and costs, reliability (as determined from other users), compatibility with existing equipment, installation requirements and cost, and to include these in the decision on the first choice. Visits to other users of the proposed equipment can be valuable for assessing ease of use, reliability and the standard of service support. A purchase order can then be issued for the equipment. At this stage, the installation issues should be clear and a specification for the building and electrical works can be drawn up by the Estates Department. This can be issued to contractors approved by the hospital and quotations invited by a given date. Site visits by potential equipment suppliers and contractors are important to ensure the quality of quotations. These can be evaluated by the project team, contracts issued to the successful contractors and the first meeting of the larger team convened to draw up a timetable for the development, taking account of delivery dates and the possible need to modify the clinical service. The progress of the project should be monitored at regular intervals through project team meetings with reports to the responsible hospital officer. Contact persons must be available to the supplier and contractors to respond to technical issues and to minimise any interference with ongoing clinical services.

1.4.2. Major capital schemes

For a major capital scheme, a more complex procedure employing external expertise is necessary. The project team will need to draw up a design brief with an outline of the scheme including the building, equipment and siting requirements, together with an overall indication of cost. Expressions of interest to design and manage the project will be invited from suitably experienced organisations through an advertisement in OJEU. These expressions of interest are evaluated by the project team and a shortlist (usually three organisations) is invited to make presentations to the project team with more details of their design, proposed management of the project, professional expertise available and fee structure. The hospital will then enter into a contract with the successful organisation and in all probability their architect will become the project manager and lead the design team. The design will begin with general layouts which will be evaluated for their workability, relationship to existing facilities and appearance. Having selected an optimal layout, the design details will be developed into plans and room data sheets by the design team. These will be supported by structural, mechanical and electrical plans developed by the architect's team and consulting engineers. Once the plans and data sheets are finalised, expressions of interest can be invited from construction companies to construct the facility though an OJEU announcement. Again these expressions of interest are evaluated by the project team together with the architect, and a tender to build the facility can be issued to a shortlist (usually three) of companies with a closing date. Presentations by the shortlisted companies are very helpful in assessing previous experience in this specialised area, quality and commitment. The tenders returned will be evaluated by the larger project team for quality and price, and the construction contract issued to the successful bidder.

A specification for the equipment can be developed in parallel with the building design. This must clearly state the key features of the desired equipment and any accessories required. Expressions of interest and tenders can again be invited from equipment suppliers through an OJEU announcement or by using the framework agreement negotiated by the NHS Supply Chain. Presentations by the suppliers are helpful to learn more about the equipment and options available and for the supplier to inspect the proposed site. The tenders returned by the closing date will be evaluated by the radiotherapy and medical physics members of the larger project team for compliance with the specification. Again, the users should develop an option appraisal pro-forma in which each of the identified performance parameters is given a weight according to their relative importance. Each performance parameter can then be scored over a given range for each equipment supplier on the basis of how closely it matches the desired performance and a weighted total score calculated to indicate which supplier's equipment most closely approaches the ideal solution. It will also be necessary to look at other issues such as operator training, maintenance training, reliability (as determined from other users), compatibility with existing equipment, installation requirements and cost, and to include these in the decision on the first choice. Again, visits to other users of the proposed equipment can be valuable for assessing ease of use, reliability and the standard of service support. A purchase order can then be issued for the equipment. In some instances, the equipment will be supplied as part of a wider national initiative. There is usually some flexibility within these arrangements to ensure that the recipient receives equipment which meets the local requirements and is compatible with existing equipment. In these circumstances, a pro-forma should be used for an option appraisal of the alternatives from different suppliers in order to reach an objective conclusion. This can be a helpful summary of the reasons for the first choice if unsuccessful suppliers ask for the reasons why they were unsuccessful. In general, it is desirable to complete the selection of the equipment before the design and room data sheets are finalised, so that any detailed requirements relating to specific equipment, e.g. the position of primary shielding in relation to the treatment isocentre, may be incorporated into the latter before tenders are issued.

1.4.3. Public private partnership

For a PFI, the Trust project team will need to draw up a comprehensive brief for the services to be provided by the new facility. This will require estimates of future growth to ensure that the facility remains clinically sufficient over the long period of the contract, but should be as accurate as possible to minimise costs and future charges. Similarly equipment requirements should be realistic and not excessive. Expressions of interest to design, construct and manage the project will be invited from suitably experienced consortia through an advertisement in the OJEU. These expressions of interest are evaluated by the project team and a shortlist (usually three consortia) is invited to make presentations to the project team with more details of their design, proposed management of the project, professional expertise available and costs. The hospital will then enter into negotiation with the preferred consortium to finalise all aspects of the project. If this is successful, a contract will be awarded to the successful bidder and in all probability their architectural practice will become project manager and lead the design work. The design will need to be evaluated for its ability to meet the specification now and in the future, its relationship to existing facilities and compliance with a wide range of regulations. Having selected an optimal layout, the design details will be developed into plans and room data sheets by the design team. These will be supported by structural, mechanical and electrical plans developed by the architect's team and consulting engineers. The equipment supplier will in all probability be a sub-contractor to the construction element of the consortium and it is important to ensure that the equipment requirements are clearly understood by the supplier and not altered in the supply chain.

1.5. Construction

The steps in the construction of a facility, the selection of equipment, and its installation and commissioning for safe clinical use are shown in figure 1.1.

Figure 1.1.

Figure 1.1. Flow chart showing the stages in building and equipment procurement and commissioning for clinical use.

Standard image High-resolution image

In a major capital scheme, regular design team meetings with the building contractor are essential during construction, in particular as the construction nears completion and more questions on detail arise. Attention to radiation protection issues is important during the construction of shielding. During the pouring of concrete bunkers for linear accelerators, samples will be taken at regular intervals for analysis, usually to check mechanical properties. It is also important to have the density of these samples measured to ensure that the density of the concrete is not less than that assumed in the shielding calculations. It is also important to check that the shielding is not compromised by joints in the concrete or block work, ducts for services or the position of shuttering bolts. These matters are dealt with in greater detail in chapter 7. As construction nears completion it is important to check that engineering controls and warning signs are sited according to the plans. At this stage, the details for the delivery of the equipment can be finalised with the supplier's representative. For a new linear accelerator, the base frame will be installed as construction nears completion, but all suppliers will only deliver the accelerator and other components to a virtually complete and clean bunker to avoid problems caused by dust, etc. Once the site is clean, the equipment can be installed and connected by the supplier's engineers and the programme to make the equipment operational started. During construction, it is also important to have a day-to-day link with the patient services manager to ensure that the construction work is phased to minimise any impact on ongoing clinical services.

For a PFI project, the responsibility for construction will lie with the construction company and compliance with the plans will be the responsibility of the design team and consultants, but will have the same emphasis as that outlined above.

1.6. Acceptance and handover

1.6.1. Buildings and services

For a major capital scheme, acceptance of the building and services will be undertaken by a hospital team including senior staff who will be working in the new facility. 'As built' plans of the facility must be handed to the hospital. A detailed inspection of the facility should take place and be compared with the plans and room data sheets. A snagging list of all defects should be drawn up and a timetable to remedy them agreed with the construction company.

Similar arrangements apply for a PFI scheme. However, whereas in a major capital scheme the maintenance of the new facility will be by the hospital's Estates Department, in a PFI scheme the responsibilities will be borne by an external maintenance contractor. Details such as the warranties on service equipment, e.g. air conditioning plant, need to be passed to the appropriate organisation.

1.6.2. Radiotherapy treatment facilities

The acceptance of radiotherapy treatment facilities will be undertaken by the RPA, checking the adequacy of the radiation protection for staff and members of the public, and an MPE radiotherapy physicist, with the assistance from other members of the radiotherapy physics team, checking the performance of the equipment against its specification.

Acceptance should begin with a basic radiation protection survey by the RPA of the shielding provided by the facility when the installation engineer states that the installation can produce radiation. At this stage, although installation is complete and the equipment operational, its radiation performance will not be optimised to match the specification. This survey should ensure that external dose rates are acceptable over a range of equipment orientations and that the facility is safe to operate for an extended series of tests. Engineering controls and warning signs should also be checked for correct operation. Electrical safety tests should also be performed at this stage to ensure that the equipment does not present an electrical hazard to the acceptance team. The latter testing may be done by the clinical engineering section of the medical physics department or by the hospital's electromedical equipment maintenance department.

A more detailed radiation protection survey should be performed following the acceptance procedure, when it is confirmed that the equipment performance, in particular beam energies and dose rates, matches the specification. External dose rates should be measured over a range of equipment orientations with and without scatter material in the radiation beam at the isocentre. Measured dose rates can then be compared to those in the radiation protection calculations to assess compliance with the calculations and any assumptions. More details on performing a radiation survey are given in chapter 12.

During the acceptance, a critical examination as required by the Ionising Radiation Regulations (IRR 1999) should be carried out by the supplier to confirm that the intended radiation protection and safety features incorporated into the equipment and its operation are satisfactory in the current installation. The examination may be performed by a representative of the equipment supplier or by the RPA at the request of the supplier.

In PFI projects, the radiation protection surveys may be undertaken by the construction company's RPA as part of their contract with the company. Alternatively, they can be done by the hospital's RPA to a protocol agreed with the constructor's RPA and with the constructor's approval. The latter is often more convenient if surveys are done at short notice. In either situation, the results of surveys should be approved by both RPAs and be generally available to show that the facility complies with national regulations and the hospital's policy on radiation protection.

Following acceptable outcomes for the basic radiation protection survey and electrical safety testing, acceptance testing of the mechanical and radiation performance of the equipment can then commence safely. Joint acceptance testing with the equipment supplier's installation engineer using the supplier's test pro-forma is commonplace. This will cover a wide range of parameters and the acceptable tolerances will be given in the pro-forma. As each test is passed within tolerance, it should be signed off by the supplier's engineer and the radiotherapy physicist. This is better than gathering a large amount of data for subsequent analysis and approval. If the equipment fails a test, further adjustment will be necessary, which may impact on tests already performed and render them invalid. Ideally all tests should be done as a complete set with no intervening adjustments to settings. At the conclusion of testing, the equipment may be accepted as meeting the specification, accepted subject to a small list of remedial actions, or not accepted because of non-compliance with a performance parameter of major importance or a long list of faults requiring remedial action. In the second case, time scales should be agreed for correcting the defects. In the third case, a new joint acceptance procedure is necessary after the installation engineer has corrected the problem(s). The final section of the joint acceptance pro-forma should reflect this situation and must be signed by both the installation engineer and responsible physicist. Following successful acceptance, this section will be the basis for further payment to the supplier for the equipment.

1.7. Commissioning

1.7.1. Clinical services

Following handover of the facility, reconfiguration of clinical services may be necessary. This should be done by the senior oncology staff involved taking into account all the relevant factors and a clear timetable developed to make all staff aware of the changes and their role in them.

1.7.2. Equipment commissioning

Following acceptance of the equipment, further commissioning will be necessary before it enters clinical use. This includes the gathering of detailed information on equipment characteristics and radiation beams for treatment planning systems, absolute calibrations of radiation output, establishment of quality assurance protocols, establishment of clinical treatment protocols and operator training. It should be understood that in the interests of patient safety, commissioning cannot be shortened to make up for any earlier delays in construction, etc.

1.8. Project evaluation

NHS Trusts are required to evaluate and learn from their projects. This is mandatory for projects over £1M and a report must be made to the Department of Health for projects over £20M. An initial evaluation should be performed 6–12 months after commissioning and a long term evaluation two years after commissioning. The evaluation should cover the following areas:

  • •  
    Brief description of project.
  • •  
    Accuracy of the original strategic context.
  • •  
    Correctness of option appraisal.
  • •  
    Review of procurement process including comparison with estimated costs.
  • •  
    Review of project management including compliance with the planned timetable.
  • •  
    Realisation of benefits.
  • •  
    Outcome and impact.
  • •  
    Lessons for future projects.

More details on project evaluation are given in (NHS Trust Development Authority 2014).

References

Export references: BibTeX RIS