To be able to compete, every micro and small enterprises (MSE) must continue to innovate in both product and production process innovation. Silver 999 is MSE which produces jewellery from gold, silver, brass and other raw materials. MSE Silver 999 products have penetrated international markets. The initial layout condition on the Silver 999 production floor was very inefficient because the Blanding work station was located outside the production area which caused the length of material flow to produce rings to be 51.35 meters. Due to improvements in some work equipment on the MSE production floor, it is necessary to redesign the layout to minimize material flow. By using a combination of the Systematic Layout Planning Method and the BLOCPLAN 90 software, a new layout proposal was obtained. By implementing the new layout, the material flow distance for ring production was reduced from 51,350 meters to 23,005 meters, or by reducing the distance by 55.2%.