A Simulation Study of Duration-Budget Trade-Off in Home Renovation Project Management

Published under licence by IOP Publishing Ltd
, , Citation Rani Purbaningtyas 2021 J. Phys.: Conf. Ser. 1817 012018 DOI 10.1088/1742-6596/1817/1/012018

1742-6596/1817/1/012018

Abstract

This paper simulated home renovation project management with 15 work items to complete. All work items are depicted in a network diagram to help the project planner manage the house renovation project. CPM/PERT helps the project planner to determine the duration of work and the costs involved. CPM/PERT shows the period needed based on the critical path obtained is 40 days, with a cost requirement of IDR 89,750,000. The project crashing technique shortened the project's duration to 25 days, with an estimated total cost of IDR 112,100,000. The cost calculations for CPM/PERT and project crashing use the Activity Based Costing (ABC) method. This paper examines how to shortened duration impact the overall budget. Both the client and contractor can get an idea of how to complete the house renovation project and the cost requirements that accompany it.

Export citation and abstract BibTeX RIS

Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.

Please wait… references are loading.