Abstract
The PICOLON project is developing a high purity NaI(Tl) crystal by optimizing the purification methods. The reduction method for 40K was established and we got sufficiently pure NaI(Tl) crystal for 40K. On the other hand, the concentration of 210Pb is still higher than our goal. The investigation is now in progress to fix the origin of the contamination.
The construction of the second phase detector system of PICOLON detector will be started in 2020 spring. The total mass of the second phase is about 54 kg. The background level by the test measurement using a single module is reported.
Export citation and abstract BibTeX RIS

Content from this work may be used under the terms of the Creative Commons Attribution 3.0 licence. Any further distribution of this work must maintain attribution to the author(s) and the title of the work, journal citation and DOI.